The Griffin Road Drainage Improvements project was completed within the City of Chipley to increase drainage capacity and relieve flooding in the Griffin Road area. The work centered on a new double-barrel concrete box culvert and new lateral ditch excavation, along with the roadway, utility, and restoration work required to finish the improvements.
GCUC delivered the full package in an active municipal corridor: the double 10′ x 7′ box culvert, roughly 550 linear feet of new lateral ditch, roadway excavation and reconstruction, guardrail, riprap erosion protection, pavement markings, sod and site restoration, and a directional-bore relocation of the 8″ water main. Work began in February 2026.
Built to Handle the Storm
A double-barrel concrete box culvert and new lateral ditches
give the Griffin Road area the drainage capacity it needed.
Scope of Work
Drainage
- Construction of a new double 10′ x 7′ concrete box culvert
- Approximately 550 linear feet of new lateral ditch excavation
- Riprap rubble placement for erosion protection
Roadway
- Roadway excavation and reconstruction at the new box culvert
- Guardrail installation
- Thermoplastic pavement markings
Utilities and Restoration
- Relocation of approximately 100 linear feet of 8″ water main by directional bore
- Sodding and site restoration
Project Gallery
Aerial and ground-level views of Griffin Road, from the first day on site through the finished crossing.
Start Your Next Project
GCUC has delivered site development and underground utility packages across the Florida Panhandle since 1999. Let’s talk about yours.
Panama City (850) 265-9166 · Milton / Pensacola (850) 665-4046